Projects > Project plan / Set estimated dates

Set estimated dates

Estimated completion dates are a tool to monitor project progress. Compare planned and estimated dates of tasks to take timely action to meet deadlines.

You can work with estimated dates if a task has the Task or Milestone type and the status In progress. Initially, in such a task, the estimated dates are set by default and coincide with the planned dates. However, in the course of the project, the manager can request the updated estimated dates of their tasks from the participants, as well as change them independently.

You can view the estimated dates on the plan chart. To do this, open the plan for editing and select the Estimation option on the toolbar in the left corner.

est_dates01

Change estimated dates

A manager with the rights to edit a plan can update the estimated dates. To do this, go to the plan editing mode and select a convenient method:

  • On the toolbar in the left corner, select the Estimation option. The chart will display the estimated dates of the tasks. Then pull the edge of the task segment. Its start and end dates will change;

est_dates02

  • Open the task page in the plan. To do this, move the cursor over its name, click the three dots icon, and select Open. Then set new values in the Start date (Estimated) and End date (Estimated) fields

est_dates03

Request estimation

If you have the rights to edit the plan, you can send a request to project participants to set estimated dates for their tasks. To do this, open the published version of the plan for editing and click Request Estimation.

In the opened window, you will see a list of tasks with Task and Milestone types and In progress status

You can sort the tasks by descending or ascending values in the selected column of the table. To do this, click on the column name, and then to the right of it click forecast-dates-7 or forecast-dates-8.

Form a request:

  • Select the tasks by marking the checkboxes to the left of their names.
  • In the Executor field, by default, the person responsible for the task is specified. You can select another project participant.
  • Specify a deadline for the request and a description.

Click Send. The specified executors will receive the corresponding task.

est_dates04

Perform the task to set an estimated date

A project participant will receive a request for estimated dates in the form of a task that contains a link to the project plan and a list of plan tasks.

You can sort the tasks by descending or ascending values in the selected column of the table. To do this, click on the column name, and then to the right of it click forecast-dates-7 or forecast-dates-8.

To run the request:

  1. Specify the deadlines in the Start (Estimated) and End date (Estimated) fields.
  2. Add a comment for each task.
  3. Click Send Estimation.

est_dates05

The new estimated dates can then be viewed:

  • In the project plan opened for editing in the Estimation mode.
  • In the task page, if you open it in the plan chart..

The task executor will receive a notification about the change of the estimated dates.

Compare estimated dates with planned dates

To visually compare the estimated dates with the planned dates:

  1. Open the plan for editing.
  2. From the toolbar in the left corner, select Estimation to display the forecast dates on the plan.
  3. Click the gear icon and enable the Compare with the current one option. The planned task dates are marked on the chart with yellow shading.

est_dates06